comes to an end in Sept 2010.
The ProCure21 Team: Peter Sellars, Dep Director of Gateway Reviews and Estates and Facilities Division, Head of ProCure21 Ray Stephenson, Programme Manager Nigel Dorman, Head of Construction Performance Barry Allsop, Cost and Performance Manager Cliff Jones, Senior Policy and Performance Manager Sean Coughlan, ProCure21 Re-let Project Director Patrick Nolan, ProCure 21 Implementation Advisor - North East Terry Finch, ProCure 21 Implementation Advisor - North West Andy Mitchell, ProCure 21 Implementation Advisor - Midlands and South West David Scammell - ProCure21 Implementation Advisor - Midlands and Eastern Peter Ramrayka - ProCure21 Implementation Advisor - London and South East Julian Colaco, Training and Communications Manager Stuart Robinson, Business Manager NHS ProCure21 Helpdesk NHS ProCure21 |
NHS ProCure21 current status
6 phase 1 (soc)
98 phase 4 (construction)
65 schemes complete under £1m
Accolade for NHS ProCure21
“The Trust’s ongoing plans meant it needed these wards operational by April 2009. Without using ProCure21 it would not have been possible. The selection process and the partnering approach saved at least six months on traditional timescales.”
Graham Marsh
Project Director, Gloucestershire Hospitals NHS Foundation Trust
Principal Supply Chain Partners (PSCPs)
|